Eichler Kitchen Remodel

(Click on the pictures to see larger versions.)

Country
			Kitchen

BEFORE REMODEL

We spent a lot of time examining options and getting bids. The main thing we knew is that the “country style” kitchen that was in the house when we bought it had to go.

Eventually we decided to save money by being our own general contractor, doing the things we knew how do to ourselves and only contracting out the stuff we couldn't do. We saved enough on the rough work and electrical that the budget allowed for custom built cabinets.

Old cabinets
			removed So here is the old kitchen after removal of the “country” cabinets. Since the old cabinets were in good condition (just not the right style) we removed them carefully to avoid damage and then donated them to a charity that could use them.

Opening up the roomOriginally there was a wall between the front door and the kitchen that ended at the beams. The opening at the top of the wall allowed light into the kitchen and gave it a open feeling. The previous kitchen remodel closed off the clerestory opening isolating the kitchen and requiring more artifical light. We decided to remove that non-load bearing wall. This gives a lot more natural light into the kitchen and it allows the multipurpose room to have a full view of the courtyard. As an added bonus we did not expect, this change brought the living room back into the house. Before it felt very isolated.

Walls
			gutted We found that in our city we could have replaced the existing cabinets without pulling a permit. However by opening up the wall we expanded the project to the point that a permit was required and that we would need to upgrade the electrical to modern standards. Fortunately there was an unused conduit from the main breaker box to the kitchen wall, so we could pull the new power wires into the area easily. We even discovered that the original telephone line was run to the island area through a conduit so we were able to pull Ethernet network wiring to our new breakfast/bill paying table on the end of our new island.

On roof
			electrical The big problem on electrical was the roof. We needed to relocate the light switches and that meant changing where the wiring dropped out of the roof. We wanted to add new lights over the island as well. After as much procastination as possible we finally marked off on the roof where the old wires came up and started in with a Sawzall. A very scary thing to do. Fortunately it all worked out and we were able to get the electrical in and inspected and the roof repaired between rain storms. In the process of doing the roof electrical work we discovered that we have one inch of rigid foam insulation. That was a nice discovery.

By the way, this picture was taken when we were just getting started on the cutting and removal of the old wire. Between other wire removal and cutting trenches for the new island lights, the final cuts were about three times as long as shown here.

Starting to take shape And once we completed the rough electrical, rough plumbing, drywall and painting the cabinets could go in. The final measurements for the cabinets could not be made until we had finished, so there was some on-site fitting that was needed. Michael Fitzgerald of Design Craft Woodworks not only helped design a wonderful set of custom kitchen cabinets but saw to it that the installation was exactly what we wanted

Once the cabinets and countertops were in we had more work to do: Install the appliances and all the under sink plumbing (including water filter).

We are very happy with the final results:

Finished Kitchen Finished Kitchen

Valid HTML 4.0! Valid CSS! Is your web browser broken?